We expected this process to be messy since there was no sheathing underlayment, just cedar shingles nailed right onto the slats. In preparation for the amount of debris that would be falling in, we pulled everything out that was on the floor and then tarped down the walls to create "slides" for debris to end up (mostly) in the center of the floor.
Tarping the Garage Walls |
This system worked fairly well and got easily 9/10's of the debris. We still had to clean off the beams and some of the edges of the walls, but most of the gunk landed right where we wanted it and easy to sweep up.
The re-roof took approx 1.5 days. The first day was tear-off of the old roofing, cleaning and repair of some damaged spots by termites and rot, followed by new sheathing. The second day, they put down the tar paper and shingles.
Ready to Start Sheathing |
Whirlybird Goes Here! |
Almost Finished! |